Collinsville
Status: COMPLETE
Allocation: $ 239,286.73
Project Description:
Downtown:
Construction of the first phase of the Main Street Master Plan Enhancements was completed in October 2008.
Neighborhoods:
The City along with the Collinsville Public Schools have upgraded the surfaces of tennis courts at the Collinsville City Park and were reimbursed with Vision 2025 funds. This project was completed in January 2010.
Design:
LandPlan Consultants
Construction:
Bryant & Bryant Cosntruction, Inc.; John Henzel Tennis Court Systems, Inc.