Osage Trail
Allocation: $3,700,000.00
Summary Update:
Trail construction was completed in August 2006. Enhancements to the Skiatook trailhead park at Highway 20, funded by Vision 2025, are complete. The remaining funds are currently anticipated for use in matching future grant funds and enhancements.
Vision 2025 funds constructed a multiuse trail along what was previously the Osage Railroad in Tulsa and Osage Counties, providing opportunities for transportation, recreation and exercise. The trail is a scenic and safe connection for users traveling north from the OSU-Tulsa campus to 56th Street North to Highway 20 in central Skiatook, with recreational and fitness opportunities along the way.
Design Advisory: Rich Brierre, INCOG
Landscape Architect: LandPlan Consultants, Inc.
Construction: Horizon Construction, Inc.