Owasso Medical Complex
Allocation: $4,500,000.00
Summary Update:
The 2.0MG Elevated Water Storage Tank was completed in July 2005. The North Service Area Transmission Line Phase I was completed in October 2005. The North Service Area Transmission Line Phase II was completed in December 2006.
Background:
As one component to this water utility project, the City awarded construction of a $1.8 million 2.0MG elevated water storage tank. This overall infrastructure project was partialy funded by Vision funds and partially by a loan from the Oklahoma Water Resources Board.