Projects

Mohawk Park

Allocation: $6,400,000.00 Summary Update: The Oxley Nature Center Building exterior renovations were completed in December 2006. The Center’s interior refurbishing was completed February 2009. The North Tulsa Sports Complex was completed in November 2012. Background: Mohawk Park encompasses several of…

Osage Trail

Allocation: $3,700,000.00 Summary Update: Trail construction was completed in August 2006.  Enhancements to the Skiatook trailhead park at Highway 20, funded by Vision 2025, are complete.  The remaining funds are currently anticipated for use in matching future grant funds and…

Low-Water Dams

Allocation: $5,600,000.00 Status: In Progress Summary Update: The success of Zink Lake in Tulsa inspired this proposal for more in-river, low water dam (LWD) sites on the Arkansas River.  The Arkansas River Corridor Master Plan (INCOG, 2005) would be the…

Route 66

Allocation: $15,000,000.00 Summary Update: As restoration and enhancements have revitalized the highway, they have met great enthusiasm from longtime supporters, and have also drawn the attention of many who are not familiar with the rich history.  As a result, informative plaques and commemorative…

Oklahoma Aquarium

Allocation: $12,000,000.00 Status: COMPLETE Summary Update: The final fund transfer was completed in June 2016. Background: Vision 2025 provides $12 million over approximately 13 years to retire the construction debt incurred to create this unique facility. The Oklahoma Aquarium is…